KEPRION
Logbook / NGT-D-0723
TB
NGT-D-0723 06:00 — 18:00 Open
Northgate Transit Hub — Structural Steel Erection · 2026-07-23
Crew
MR
M. Reyes (Foreman)
TO
T. Okonkwo
DB
D. Braun
SW
S. Whitecloud
PL
P. Larsson
AG
A. Gupta
+3 more
14 entries
MR
M. Reyes (Foreman)
Signed Off
Completed bolt-up of column line C, grid 4–7. Torqued A325 3/4 in. bolts to full proof load; slip-critical connection verified. 3 crew on deck. All connections inspected by foreman, compliant per spec IFC-SC-14.
#14
Within Tolerance Foreman Sign-Off
Plumb & align check on bay B2 — column C4 and C5 both within L/1000 tolerance per AISC 303. Reading: 3 mm drift over 9.6 m column height. Signed off by foreman M. Reyes. Ready for decking gang.
+3
#13
Late Entry
Steel delivery received at 11:48 — 12 beams W18×35, heat no. H2-4471. Beams tagged, staged in east lay-down zone, row 3. 3 beams noted with minor mill scale on flanges; recorded for inspection, no rejection. BOL #SL-2026-0849 signed.
#12
NDT Pass
Weld inspection — ultrasonic testing (UT) on moment connection MC-14, joint W24×104 beam-to-column. Inspector: R. Takahashi (CWI cert. #8821). Result: PASS — no rejectable indications per AWS D1.1 clause 6.13.3. Report no. NDT-NGT-0141 filed.
#11
All Compliant
100% tie-off audit conducted on all ironworkers in the Raising Gang — 9 workers on elevated steel above 6 ft. All harnesses, lanyards, and anchorage points inspected. Zero deficiencies found. Audit logged per OSHA 1926.502(d). Next audit scheduled for 13:00.
#9
Rigging Cert.
Rigged and set columns C4 and C5 (W14×132, 9.6 m, approx. 1 820 kg each). Twin 25-tonne wire rope slings used; lift plan LP-NGT-031 followed. Both columns plumbed and temporarily braced; bearing pads leveled prior to erection. Crane picks: 2 of 2 complete.
#6
Auto-Logged
Shift NGT-D-0723 opened at 2026-07-23 06:04. Crew check-in: 9 ironworkers confirmed. Site conditions: clear, 18°C. JHA reviewed at tailgate — all hands signed.
#1
Shift Summary
Shift Date 2026-07-23
Duration 08:32 / 12:00 h
Total Entries 14
Crew on Deck 9
Status Open
Flagged Items 0
By Process Area entries
Bolt-Up 4
Plumb & Align 2
Rigging 2
Safety 2
NDT Inspection 1
Delivery 1
General 2
References
Lift Plan LP-NGT-031
IFC-SC-14 (bolt-up spec)
NDT Report NDT-NGT-0141
BOL #SL-2026-0849